Glossary
Glossary of Chilean land and permitting terms for energy developers
Chilean land, registry and permitting terms in Spanish, English and Chinese, each with a one-sentence definition. The Spanish term is the one used in Chilean law and in the documents you will sign.
| English | Español | 中文 |
|---|---|---|
| Apostille (apostilla) | Apostilla | 附加证明书(apostilla,海牙认证) |
| Appraisal commission (comisión tasadora) | Comisión tasadora | 评估委员会(comisión tasadora) |
| Archaeological monument (monumento arqueológico) | Monumento arqueológico | 考古遗迹(monumento arqueológico) |
| BESS (battery energy storage system) | BESS (sistema de almacenamiento de energía en baterías) | 电池储能系统(BESS) |
| Border zone (zona fronteriza) | Zona fronteriza | 边境地区(zona fronteriza) |
| Boundaries (deslindes) | Deslindes | 地界(deslindes) |
| Certificate of current title (certificado de dominio vigente) | Certificado de dominio vigente | 现行产权证明(certificado de dominio vigente) |
| Co-ownership (comunidad) | Comunidad | 共有(comunidad) |
| DDU 522 circular (Circular DDU 522) | Circular DDU 522 | DDU 522号通函(Circular DDU 522) |
| Direct agreement (acuerdo directo) | Acuerdo directo | 贷款人直接协议(acuerdo directo) |
| DL 2.695 title regularization (Decreto Ley 2.695) | Decreto Ley 2.695 (regularización de la pequeña propiedad raíz) | 第2.695号法令(Decreto Ley 2.695) |
| Easement (servidumbre) | Servidumbre | 地役权(servidumbre) |
| Easement strip, right-of-way (franja) | Franja de servidumbre | 线路走廊(franja de servidumbre) |
| Electric concession (concesión eléctrica) | Concesión eléctrica | 电力特许权(concesión eléctrica) |
| Encumbrance certificate (certificado de hipotecas y gravámenes) | Certificado de hipotecas, gravámenes, interdicciones y prohibiciones | 抵押、负担及禁止事项证明(certificado de hipotecas y gravámenes) |
| Environmental approval (Resolución de Calificación Ambiental, RCA) | RCA (Resolución de Calificación Ambiental) | 环评批复(Resolución de Calificación Ambiental,RCA) |
| Environmental impact assessment system (SEIA) | SEIA (Sistema de Evaluación de Impacto Ambiental) | 环境影响评价系统(SEIA,环评) |
| Equator Principles | Principios de Ecuador | 赤道原则(Equator Principles) |
| Forest management plan (plan de manejo) | Plan de manejo (CONAF) | 森林管理计划(plan de manejo) |
| Full environmental impact study (EIA) | EIA (Estudio de Impacto Ambiental) | 环境影响研究(完整版,EIA) |
| Gen-tie line (línea de conexión) | Línea de conexión (gen-tie) | 送出线路(gen-tie,línea de conexión) |
| Grant of heirship (posesión efectiva) | Posesión efectiva | 继承确认(posesión efectiva) |
| IFC Performance Standard 5 (PS5) | Norma de Desempeño 5 de la IFC (PS5) | 国际金融公司绩效标准5(IFC PS5) |
| Independent system operator (Coordinador Eléctrico Nacional, CEN) | Coordinador Eléctrico Nacional (CEN) | 智利国家电力协调中心(Coordinador Eléctrico Nacional,CEN) |
| Indigenous consultation (consulta indígena) | Consulta indígena | 原住民协商(consulta indígena) |
| Indigenous lands (tierras indígenas) | Tierras indígenas (Ley 19.253) | 原住民土地(tierras indígenas) |
| Interconnection request (Solicitud de Autorización de Conexión, SAC) | Solicitud de Autorización de Conexión (SAC) | 并网接入申请(Solicitud de Autorización de Conexión,SAC) |
| Land option (opción de arriendo) | Opción de arriendo | 土地租赁选择权协议(opción de arriendo) |
| Land registry (Conservador de Bienes Raíces, CBR) | Conservador de Bienes Raíces (CBR) | 不动产登记处(Conservador de Bienes Raíces,CBR) |
| Land-use plan (plan regulador comunal, intercomunal or metropolitano) | Plan regulador (PRC, PRI, PRMS) | 市镇/跨市镇/大都市区规划(PRC、PRI、PRMS) |
| Lease (arriendo) | Arriendo (arrendamiento) | 土地租赁(arriendo) |
| Marital community property (sociedad conyugal) | Sociedad conyugal | 夫妻共同财产制(sociedad conyugal) |
| Mining concession (concesión minera) | Concesión minera | 矿业特许权(concesión minera) |
| Negotiated easement (servidumbre voluntaria) | Servidumbre voluntaria | 协议地役权(servidumbre voluntaria) |
| Notary (notario) | Notario | 公证人(notario) |
| Open access (acceso abierto) | Acceso abierto | 开放接入(acceso abierto) |
| PAS 160 (Art. 55 approval within the SEIA) | PAS 160 | PAS 160(环评程序中的第55条许可) |
| Promise to contract (promesa) | Promesa de contrato | 预约合同(promesa de contrato) |
| Public deed (escritura pública) | Escritura pública | 经公证的契据(escritura pública) |
| Real right (derecho real) | Derecho real | 物权(derecho real) |
| Recording (inscripción) | Inscripción | 登记(inscripción) |
| Restriction on encumbrance and transfer (prohibición de gravar y enajenar) | Prohibición de gravar y enajenar | 禁止设定负担及转让(prohibición de gravar y enajenar) |
| Rural construction approval (Art. 55 LGUC report, IFC) | Informe favorable del artículo 55 LGUC (IFC) | 农村非农建设许可意见(第55条,IFC) |
| Rural parcel (predio rústico) | Predio rústico | 农村地块(predio rústico) |
| Rural subdivision rules (Decreto Ley 3.516) | Decreto Ley 3.516 (división de predios rústicos) | 第3.516号法令(Decreto Ley 3.516) |
| Screening opinion request (consulta de pertinencia) | Consulta de pertinencia | 是否须进入环评的咨询(consulta de pertinencia) |
| Short-form environmental impact statement (DIA) | DIA (Declaración de Impacto Ambiental) | 环境影响声明(简式,DIA) |
| Site control (título habilitante) | Título habilitante sobre el terreno | 场址控制(título habilitante) |
| Small distributed generation (PMGD) | PMGD (pequeño medio de generación distribuida) | 小型分布式发电(PMGD) |
| State land concession (terreno fiscal, Bienes Nacionales) | Terreno fiscal (concesión de Bienes Nacionales) | 国有土地有偿使用特许(terreno fiscal,Bienes Nacionales) |
| Statutory electric easement (servidumbre legal eléctrica) | Servidumbre legal eléctrica | 法定电力地役权(servidumbre legal eléctrica) |
| Surface right (derecho de superficie) | Derecho de superficie | 地上权(derecho de superficie) |
| Tax roll number (rol de avalúo) | Rol de avalúo (rol SII) | 税务局不动产编号(rol de avalúo) |
| Title study (estudio de títulos) | Estudio de títulos | 产权调查(estudio de títulos) |
| Transmission corridor study (Estudio de Franja) | Estudio de Franja | 线路走廊研究(Estudio de Franja) |
| UF (unidad de fomento) | UF (unidad de fomento) | UF(unidad de fomento) |
| Under-construction declaration (declaración en construcción) | Declaración en construcción | 在建项目认定(declaración en construcción) |
| Usufruct (usufructo) | Usufructo | 用益权(usufructo) |
| Water use right (derecho de aprovechamiento de aguas) | Derecho de aprovechamiento de aguas | 水资源使用权(derecho de aprovechamiento de aguas) |
| Zoning certificate (Certificado de Informaciones Previas, CIP) | Certificado de Informaciones Previas (CIP) | 规划条件证明(Certificado de Informaciones Previas,CIP) |
Definitions
- Apostille (apostilla)
- Certificate that authenticates a public document issued in a country party to the Hague Convention, such as a power of attorney signed abroad, and replaces legalization for use in Chile. Ley 20.711Title and registry
- Appraisal commission (comisión tasadora)
- Panel of three professionals appointed by the electricity and fuels regulator (Superintendencia de Electricidad y Combustibles, SEC) that, absent agreement, sets the compensation for an electric easement without counting any increase in value from the works. Ley General de Servicios Eléctricos, arts. 63 y 63 bisEasements
- Archaeological monument (monumento arqueológico)
- Site, ruin, deposit or anthropological-archaeological object that belongs to the State by operation of law; any find must be reported to the National Monuments Council. Ley 17.288, arts. 21 y 26Permitting and land use
- BESS (battery energy storage system)
- System that stores energy in batteries to deliver it to the grid later; it can sit inside or near a substation and, since electric concessions do not cover it, its site is negotiated with the landowner. Ley General de Servicios Eléctricos, art. 2Power sector
- Border zone (zona fronteriza)
- Area declared a border zone, where nationals of neighboring countries cannot acquire ownership or other real rights in real property unless exempted by decree and where, under DL 993, rural parcels cannot be leased to foreigners. Decreto Ley 1.939 de 1977, art. 7Minerals, water and special land regimes
- Boundaries (deslindes)
- Limits of a parcel with its neighbors as stated in the recording; older recordings often describe them by the names of adjoining owners, so they are checked against a plan or a survey.Title and registry
- Certificate of current title (certificado de dominio vigente)
- Copy of a parcel’s ownership recording, certified by the Conservador as still in force, showing who the current recorded owner is.Title and registry
- Co-ownership (comunidad)
- Situation in which several people own the same property, for example the heirs of a deceased owner; in practice, all co-owners sign a lease or an easement over the parcel.Title and registry
- DDU 522 circular (Circular DDU 522)
- March 2025 circular from the Ministry of Housing and Urban Development (MINVU) that classifies standalone BESS as energy infrastructure, a use allowed in the rural areas of intercommunal plans subject to Art. 55 LGUC. Circular DDU 522, MINVU (2025)Permitting and land use
- Direct agreement (acuerdo directo)
- Agreement among the landowner, the tenant and the project lender that lets the lender cure the tenant’s defaults or step into its place before the lease is terminated.Project finance
- DL 2.695 title regularization (Decreto Ley 2.695)
- Decree-law of 1979 for regularizing possession of small properties that lack a recorded title; a title study checks the regularization order and the date it was recorded. Decreto Ley 2.695 de 1979Title and registry
- Easement (servidumbre)
- Encumbrance on a property in favor of another property or of a facility, allowing, for example, a power line or an access road to cross it.Easements
- Easement strip, right-of-way (franja)
- Strip of land along a power line that is subject to the easement, where the owner may not plant or build anything that interferes with it. Ley General de Servicios Eléctricos, art. 57Easements
- Electric concession (concesión eléctrica)
- Right granted by the State for hydro plants, substations, and transmission and distribution lines that allows the holder to impose easements; solar and wind plants are not subject to concession. Ley General de Servicios Eléctricos, arts. 2, 3 y 51Power sector
- Encumbrance certificate (certificado de hipotecas y gravámenes)
- Certificate from the Conservador listing the mortgages, easements, usufructs, attachments and prohibitions on transfer recorded against a parcel.Title and registry
- Environmental approval (Resolución de Calificación Ambiental, RCA)
- Resolution that concludes the SEIA review, approving or rejecting the project and setting the conditions under which it may be carried out.Permitting and land use
- Environmental impact assessment system (SEIA)
- Process run by the Environmental Assessment Service (SEA) in which projects of the types listed by law, such as high-voltage lines, substations and power plants over 3 MW, are assessed through a DIA or an EIA. Ley 19.300, art. 10Permitting and land use
- Equator Principles
- Environmental and social risk framework that signatory banks apply to project finance; Chile is one of its Designated Countries, where compliance with local law is required. Equator Principles, Designated CountriesProject finance
- Forest management plan (plan de manejo)
- Plan that the National Forestry Corporation (CONAF) must approve before any native forest is cut, with 90 days to decide on it. Ley 20.283, arts. 5 y 8Permitting and land use
- Full environmental impact study (EIA)
- Full route into the SEIA, required when a project triggers any of the effects in Article 11 of Law 19.300, such as resettlement of communities, a location in or near protected areas or impacts on cultural heritage. Ley 19.300, art. 11Permitting and land use
- Gen-tie line (línea de conexión)
- Dedicated line that carries power from a plant or BESS to the substation where it connects to the grid; it may apply for an electric concession to obtain the statutory easement. Ley General de Servicios Eléctricos, arts. 2, 14 y 51Power sector
- Grant of heirship (posesión efectiva)
- Order that recognizes the heirs of a deceased person, similar to probate; until it is recorded along with the special recordings, the heirs cannot dispose of the estate’s real property. Código Civil, art. 688Title and registry
- IFC Performance Standard 5 (PS5)
- International Finance Corporation standard on land acquisition and involuntary resettlement that does not apply to voluntary transactions but does apply to negotiated deals where the buyer could resort to compulsory procedures, and that treats easements as land acquisition. IFC Performance Standard 5 (2012), paras. 5 and 6 and note 2Project finance
- Independent system operator (Coordinador Eléctrico Nacional, CEN)
- Independent technical body created by Law 20.936 that coordinates the operation of Chile’s power system, much like an ISO, and processes interconnection requests to the transmission system. Ley 20.936 de 2016Power sector
- Indigenous consultation (consulta indígena)
- Good-faith consultation process that the Environmental Assessment Service runs when a project under SEIA review directly affects indigenous peoples, under ILO Convention 169. Decreto Supremo 40 de 2012 (Reglamento del SEIA), art. 85Permitting and land use
- Indigenous lands (tierras indígenas)
- Land protected under the Indigenous Law (Law 19.253); community land cannot be leased, an individual’s land can be leased for five years at most, and encumbering it requires approval from the national indigenous development agency (CONADI). Ley 19.253, art. 13Minerals, water and special land regimes
- Interconnection request (Solicitud de Autorización de Conexión, SAC)
- Request to the Coordinador to connect a project to the transmission system; it does not require title to the land, but the authorization can be voided if title is not shown in time for the under-construction declaration. Decreto Supremo 37 de 2019 (Energía), arts. 15 y 25Power sector
- Land option (opción de arriendo)
- Agreement under which the owner holds land for a project in exchange for periodic option payments, and the developer may exercise it to sign a lease if the project moves forward.Contracts and property rights
- Land registry (Conservador de Bienes Raíces, CBR)
- Land registry for a comuna or group of comunas, kept by a registrar who acts as an official witness (ministro de fe); it holds the property, mortgages and encumbrances, and prohibitions registers for the real estate in its territory, indexed by the names of the parties rather than by parcel. Ley del Registro Conservatorio de Bienes Raíces, arts. 31, 32 y 41; Código Orgánico de Tribunales, arts. 446 y 447Title and registry
- Land-use plan (plan regulador comunal, intercomunal or metropolitano)
- Municipal, intercommunal or metropolitan planning instrument that sets land uses and the urban limit; outside that limit, infrastructure is subject to Art. 55 LGUC. Ley General de Urbanismo y Construcciones, art. 28Permitting and land use
- Lease (arriendo)
- Contract under which the owner grants the use of the land in exchange for rent; if executed by public deed it binds a later buyer and, if recorded before the mortgage, the mortgage lender too. Código Civil, art. 1962Contracts and property rights
- Marital community property (sociedad conyugal)
- Marital property regime under which, if a rural parcel is community property, the husband needs his wife’s authorization to encumber it or to lease it for more than eight years. Código Civil, art. 1749Title and registry
- Mining concession (concesión minera)
- Real property right over mineral substances, separate from and independent of ownership of the surface parcel, which subjects the parcel to mining easements against compensation. Código de Minería, arts. 2, 120 y 122Minerals, water and special land regimes
- Negotiated easement (servidumbre voluntaria)
- Easement the owner grants by agreement, on the route, terms and price the parties negotiate; it is granted by public deed and may be recorded with the Conservador. Código Civil, arts. 698 y 880Easements
- Notary (notario)
- Civil-law notary who, as an official witness (ministro de fe), drafts and authorizes public deeds and other public instruments. Código Orgánico de Tribunales, art. 399Title and registry
- Open access (acceso abierto)
- Rule under which owners of transmission facilities, except dedicated systems, cannot deny third parties access on grounds of technical capacity. Ley General de Servicios Eléctricos, art. 79Power sector
- PAS 160 (Art. 55 approval within the SEIA)
- Sectoral environmental permit that takes the place of the Art. 55 LGUC approval when a project goes through the SEIA; it requires that the project neither create new urban centers nor cause loss or degradation of soil. Decreto Supremo 40 de 2012 (Reglamento del SEIA), art. 160Permitting and land use
- Promise to contract (promesa)
- Agreement binding the parties to enter into another contract later; it is enforceable only if it is in writing, sets a term or condition and specifies the promised contract. Código Civil, art. 1554Contracts and property rights
- Public deed (escritura pública)
- Document executed before a notary and entered in the notary’s protocol, which must be written in Spanish. Código Orgánico de Tribunales, arts. 403 y 404Title and registry
- Real right (derecho real)
- Right held over a thing regardless of any particular person; the Civil Code recognizes ownership, inheritance, usufruct, use or habitation, easements, pledge and mortgage as real rights. Código Civil, art. 577Contracts and property rights
- Recording (inscripción)
- Entry of a title in one of the Conservador’s registers; ownership of real estate is transferred by recording, and possession of it can only be acquired that way. Código Civil, arts. 686 y 724Title and registry
- Restriction on encumbrance and transfer (prohibición de gravar y enajenar)
- Owner’s covenant not to mortgage, encumber or sell the parcel; once recorded in the Conservador’s prohibitions register, it appears on the parcel’s certificate. Ley del Registro Conservatorio de Bienes Raíces, arts. 32 y 53Contracts and property rights
- Rural construction approval (Art. 55 LGUC report, IFC)
- Favorable report from the regional office of the housing ministry (SEREMI MINVU) and the Agricultural and Livestock Service (SAG) that infrastructure outside urban limits needs before municipal approval; under the SAG’s procedure, the landowner files the request and soil pits are required. Ley General de Urbanismo y Construcciones, art. 55Permitting and land use
- Rural parcel (predio rústico)
- Property suited to farming, grazing or forestry; under a lease of such land the tenant cannot assign or sublease without the owner’s prior written authorization. Decreto Ley 993 de 1975, art. 7Contracts and property rights
- Rural subdivision rules (Decreto Ley 3.516)
- Decree-law that allows rural parcels to be freely divided into lots of at least 0.5 hectares, which are then barred from changing their use except as Articles 55 and 56 LGUC allow. Decreto Ley 3.516 de 1980, art. 1Permitting and land use
- Screening opinion request (consulta de pertinencia)
- Request to the Environmental Assessment Service for an opinion on whether a project, or a change to an existing one, must enter the SEIA. Decreto Supremo 40 de 2012 (Reglamento del SEIA), art. 26Permitting and land use
- Short-form environmental impact statement (DIA)
- Shorter route into the SEIA, for projects that do not trigger any of the effects, characteristics or circumstances listed in Article 11 of Law 19.300. Ley 19.300, art. 11Permitting and land use
- Site control (título habilitante)
- The set of rights a developer holds to show it can use the project site, such as an option or promise, a recorded lease, easements or a concession; the CNE requires such title to declare a project under construction. Decreto Supremo 125 de 2017 (Energía), art. 19, letra hProject finance
- Small distributed generation (PMGD)
- Generation or storage project connected to the distribution grid with surplus capacity of up to 9 MW; on private land, its connection request requires a current title certificate and a sworn statement from the landowner. Decreto Supremo 88 de 2019 (Energía), art. 43Power sector
- State land concession (terreno fiscal, Bienes Nacionales)
- State-owned land that the Ministry of National Assets can grant in concession to a Chilean legal entity, for a fee and for up to 50 years. Decreto Ley 1.939 de 1977, arts. 57, 61 y 62Minerals, water and special land regimes
- Statutory electric easement (servidumbre legal eléctrica)
- Easement that the holder of an electric concession for a line or substation may impose on third-party land without the owner’s agreement, against the compensation set by law. Ley General de Servicios Eléctricos, arts. 14 y 51Easements
- Surface right (derecho de superficie)
- Real right to build and keep structures on another’s land, which the Chilean Civil Code does not provide as a general right; in Chile, a project on private land is secured with a recorded lease and easements. Código Civil, art. 577Contracts and property rights
- Tax roll number (rol de avalúo)
- Number the Chilean tax service (Servicio de Impuestos Internos, SII) assigns to each parcel for property tax; it does not prove ownership, which rests on the recording at the Conservador.Title and registry
- Title study (estudio de títulos)
- A lawyer’s review of a parcel’s chain of ownership recordings and of its encumbrances, prohibitions, estates and signing powers, usually covering at least the ten-year period of extraordinary acquisitive prescription (Chile’s counterpart to adverse possession). Código Civil, art. 2511Title and registry
- Transmission corridor study (Estudio de Franja)
- Ministry of Energy procedure for new transmission projects that require it, with a strategic environmental assessment; the decree setting the final route creates the easement by operation of law. Ley General de Servicios Eléctricos, arts. 93, 94 y 97Easements
- UF (unidad de fomento)
- Unit of account adjusted daily for changes in the consumer price index, commonly used in Chile to set rents and long-term prices.Contracts and property rights
- Under-construction declaration (declaración en construcción)
- Act by which the National Energy Commission (Comisión Nacional de Energía, CNE) recognizes a project as under construction; it requires title to the land, such as ownership, usufruct, lease, concession or easement, or a promise relating to its use. Decreto Supremo 125 de 2017 (Energía), art. 19Power sector
- Usufruct (usufructo)
- Real right to use and enjoy another’s property while preserving it; when granted to a corporation or foundation it cannot exceed 30 years. Código Civil, art. 770Contracts and property rights
- Water use right (derecho de aprovechamiento de aguas)
- Real right to use and enjoy water, separate from land ownership; one granted by concession lasts 30 years, is renewable and is recorded in the Conservador’s water rights register. Código de Aguas, arts. 6 y 114Minerals, water and special land regimes
- Zoning certificate (Certificado de Informaciones Previas, CIP)
- Certificate issued by the municipal building department (Dirección de Obras Municipales) stating the zoning rules that apply to a parcel under the land-use plan in force. Ley General de Urbanismo y Construcciones, art. 116Permitting and land use